Flexi Versa Group
Capabilities
Industries
About UsGlobal PartnershipsNews & InsightsCareers
Contact Us
Capabilities
No links available
Industries
No links available
About Us
Global Partnerships
News & Insights
Careers
Contact Us

Nothing here yet, please check back soon.

arrow
No links available
Flex Versa Group

Capabilities
    Industries
      • About Us
      • Global Partnerships
      • News & Insights
      • Careers
      • Contact Us

      © 2026. Flexi Versa Group. All Rights Reserved.

      Privacy Policy
      |
      Terms & Conditions
      case studies

      Managing Long-Term Durability Issues in a Regulated Medical Device Box Build

      Flexi Versa Group

      Published on 23rd November 2026

      Managing Long-Term Durability Issues in a Regulated Medical Device Box Build.

      When a regulated medical device enters field use, the manufacturing relationship does not end at shipment. For OEM operations teams, the period between product release and end-of-life is where an EMS partner's true capability becomes visible: in how quickly field returns are investigated, how thoroughly root causes are documented, and whether corrective actions hold across subsequent production lots.

      This case study describes how Flexi Versa Group (FVG) managed a long-term durability issue identified in a Class II medical device box build manufactured at its Malaysia facility. All customer and product details are anonymised. The account reflects FVG's documented complaint-handling, investigation and CAPA processes as applied to a real post-market scenario.

      When a regulated medical device enters field use, the manufacturing relationship does not end at shipment. For OEM operations teams, the period between product release and end-of-life is where an EMS partner's true capability becomes visible: in how quickly field returns are investigated, how thoroughly root causes are documented, and whether corrective actions hold across subsequent production lots.

      This case study describes how Flexi Versa Group (FVG) managed a long-term durability issue identified in a Class II medical device box build manufactured at its Malaysia facility. All customer and product details are anonymised. The account reflects FVG's documented complaint-handling, investigation and CAPA processes as applied to a real post-market scenario.

      Background: Product Profile and Manufacturing Scope

      The product in question was a capital medical device box build, a self-contained diagnostic unit used in clinical environments. FVG's scope covered full box build integration, including:

      • SMT PCB assembly across multiple boards

      • Precision injection-moulded enclosure components, produced in-house

      • Electromechanical sub-assembly and cable harnessing

      • Functional test, calibration verification and final inspection

      • Serialised labelling and regulated packaging

      The product carried a two-year OEM warranty and was subject to the OEM's internal complaint management procedure, which required FVG to respond to any field-return notification within a defined escalation window and to provide documented investigation reports traceable to specific production lots and date codes.

      Production had been running for approximately 18 months across several lots when the first pattern of field returns was reported.

      The Problem: A Durability Pattern Emerges in the Field

      Over a six-week period, the OEM's field service team logged a cluster of returns from units in the same deployment region. Each unit exhibited the same symptom: intermittent loss of communication between the main control board and a secondary sensor interface module, occurring after extended continuous operation.

      Initial field diagnostics were inconclusive. The failure did not reproduce consistently on the OEM's bench test equipment, which created a significant investigation risk: without a reproducible failure mode, the root cause could not be determined and any corrective action would be speculative.

      Why This Type of Failure Is Particularly High-Risk

      Intermittent failures in regulated devices carry a specific burden of proof. Under ISO 13485 and FDA complaint-handling requirements, the OEM must document:

      1. Whether the failure represents a pattern or isolated event

      2. Whether the EMS partner's manufacturing process is a contributing cause

      3. Whether any in-field units outside the return sample are at risk

      4. What corrective or preventive action has been taken and verified

      An EMS partner that cannot provide lot-traceable production records, in-process inspection data and environmental stress test results at this stage forces the OEM to carry the entire investigation burden internally, significantly increasing cost, timeline and regulatory exposure.

      FVG's response began with a formal complaint intake logged against the relevant lot numbers, triggering its ISO 13485-aligned non-conformance procedure.

      Investigation: Structured Root Cause Analysis Under a Documented Process

      FVG initiated a structured 8D investigation, coordinated between its quality engineering team in Malaysia and the OEM's supplier quality manager. The investigation proceeded in defined phases, each with documented outputs shared with the OEM at agreed intervals.

      Phase 1: Lot Traceability and Production Record Review

      The first step was to isolate the affected production lots using FVG's serialised traceability system. Every unit produced carries a unique serial number linked to:

      • SMT production batch records, including solder paste lot, reflow profile data and AOI results

      • Component lot codes and supplier certificates of conformance

      • In-circuit test (ICT) and functional test pass/fail records

      • Operator and shift records for manual assembly stages

      • Final inspection sign-off and calibration verification data

      This allowed the quality team to determine within 48 hours that the affected units were concentrated in two consecutive production lots and to confirm that a third lot, produced after a scheduled preventive maintenance cycle on the SMT line, showed no field returns to date.

      Phase 2: Physical Failure Analysis

      Returned units were disassembled under controlled conditions. Physical inspection and electrical characterisation identified micro-cracking in solder joints at a specific connector interface on the sensor module PCB. The cracking pattern was consistent with thermally induced mechanical stress during prolonged operation rather than a process defect at time of manufacture.

      Key findings from failure analysis:

      Finding

      Detail

      Failure location

      Connector solder joints, sensor interface PCB

      Failure mechanism

      Thermal cycling fatigue, micro-crack propagation

      Time to failure

      Typically 800–1,200 operating hours in field data

      Assembly process implicated

      Initial assessment: no direct SMT process defect identified

      Design interface factor

      Connector footprint geometry creating differential thermal expansion

      Phase 3: Environmental Stress Testing

      To reproduce the failure under controlled conditions, FVG's engineering team designed a thermal cycling test protocol based on the product's documented operating environment. Test units from the affected lots were subjected to accelerated thermal cycling between the product's rated temperature extremes.

      The failure mode was successfully reproduced within the test programme, providing the documented evidence needed to confirm root cause and to validate any corrective action before implementation.

      Critical point: Reproducing an intermittent field failure under controlled conditions is a prerequisite for any credible corrective action. Without this step, a CAPA is based on assumption rather than evidence, which is specifically called out as a deficiency risk.

      Root Cause Determination: A Shared Engineering Problem

      The investigation concluded that the root cause was a design-manufacturing interface issue rather than a standalone process failure. Specifically:

      • The connector footprint on the sensor PCB had been specified with a pad geometry that, under the thermal mass distribution of the assembled board, created localised stress concentration at the joint fillet during thermal cycling

      • The IPC-A-610 acceptance criteria applied at manufacture were met; the joints were conforming at time of production

      • The failure mode only became apparent under sustained operational thermal cycling beyond what the standard functional test regime exercised

      This determination had two important consequences for the OEM. First, it meant that the manufacturing process itself was not defective and that units produced to the same process were not at general risk. Second, it identified a design-level change as the primary corrective action, requiring collaboration between FVG's process engineering team and the OEM's product design function.

      What this illustrates about EMS accountability: A less rigorous investigation might have concluded that the solder joints were "within specification" and closed the complaint without further action. FVG's process required the investigation to continue until a credible causal mechanism was identified and reproduced, even when the initial evidence pointed away from a manufacturing defect.

      Corrective and Preventive Action: What Was Implemented

      The CAPA plan was developed jointly and documented in FVG's quality management system with the OEM's approval at each stage. Actions fell into three categories.

      Immediate Containment Actions

      • Affected lot units still in FVG's finished goods inventory were placed on hold and quarantined pending disposition

      • A field communication was prepared by the OEM, supported by FVG's lot traceability data, to identify the population of in-field units from the affected lots

      • A rework protocol was developed and validated for units that could be returned for connector re-work, including updated inspection criteria and a post-rework functional test sequence

      Design and Process Corrections

      Working with the OEM's PCB design team, FVG's process engineers proposed and validated a revised connector footprint with modified pad geometry and an additional underfill process step to mechanically reinforce the joint interface. The validation programme included:

      • Build of engineering samples to the revised design

      • Accelerated thermal cycling to the same test protocol used to reproduce the original failure

      • Cross-section analysis of joints post-test to confirm absence of micro-cracking

      • Updated IPC-A-610 workmanship criteria and inspection records for the revised joint configuration

      The revised design was formally released through the OEM's engineering change control process, with FVG's process documentation updated to reflect the new build standard.

      Systemic Preventive Actions

      Beyond the immediate product correction, FVG's quality team identified two systemic improvements to prevent recurrence of similar design-manufacturing interface issues in future programmes:

      1. Design for Manufacturability (DFM) review enhancement: The DFM checklist for new medical device programmes was updated to include a thermal cycling risk assessment for connector footprint geometry on high-power or thermally active boards

      2. Test coverage review: The standard functional test regime was reviewed against the product's in-field duty cycle, and a periodic soak test step was added to the end-of-line test sequence for thermally demanding products

      Both preventive actions were documented in FVG's quality management system and made available to the OEM as part of the closed CAPA record.

      Warranty Resolution and Field Support

      Alongside the technical investigation, FVG managed the warranty return logistics and documentation in parallel to avoid delays in the OEM's field service operations.

      Return Handling Process

      Returned units were received at FVG's Malaysia facility under a documented return merchandise authorisation (RMA) process. Each unit was:

      • Logged against its serial number and cross-referenced to the original production records

      • Assessed against the failure description provided by the OEM's field service team

      • Either repaired to the validated rework standard or dispositioned as scrap, with disposition recorded in the quality management system

      • Re-tested to the full functional test specification before return to the OEM's service inventory

      The RMA process generated a per-unit disposition record for every return, providing the OEM with complete documentation of the field return population and the actions taken on each unit.

      Regulatory Documentation Support

      For a Class II medical device, the OEM is required to maintain complaint files that include records of investigation and corrective action. FVG provided the OEM with a complete investigation package, including:

      • The 8D report with all phase outputs

      • Lot traceability data linking affected units to specific production records

      • Failure analysis findings and test data

      • The validated CAPA plan and evidence of corrective action effectiveness

      • Updated process documentation reflecting the revised build standard

      This documentation package was structured to integrate directly into the OEM's complaint file, reducing the administrative burden on the OEM's quality team and ensuring the complaint record was audit-ready.

      What This Process Demonstrates for OEM Evaluators

      For OEM operations leaders and supplier quality managers evaluating EMS partners, this case illustrates several capability dimensions that are difficult to assess from a capability statement or facility audit alone.

      Capability dimension

      What this case demonstrates

      Traceability depth

      Serial-level lot traceability enabled containment scoping within 48 hours of complaint intake

      Investigation rigour

      Structured 8D process with documented phase outputs; failure reproduced under controlled conditions before CAPA was defined

      Engineering collaboration

      Root cause spanned design and process; FVG engaged at the design interface rather than closing at process conformance

      Regulatory documentation

      Complete complaint file package provided in a format compatible with OEM's quality management system

      Preventive action

      Systemic DFM and test coverage improvements documented and applied to future programmes

      Continuity protection

      RMA handling and rework validation ran in parallel with investigation to minimise field service disruption

      The Difference Between Process Conformance and Process Evidence

      Many EMS providers maintain ISO 13485 certification. Certification confirms that a quality management system exists and has been audited against the standard. It does not confirm how that system performs under pressure: when a field return cluster appears, when a failure mode is intermittent and difficult to reproduce, or when the root cause sits at the boundary between design and manufacturing.

      The evidence of EMS capability in regulated manufacturing is not found in a certificate. It is found in the quality records generated when something goes wrong: the traceability pull, the 8D report, the failure analysis data, the CAPA validation evidence, and the regulatory documentation package handed to the OEM at closure.

      For OEM teams evaluating EMS partners: the right question to ask a prospective partner is not "are you ISO 13485 certified?" but "show me a closed CAPA from a field return event and walk me through how it was managed."

      Working With FVG on Post-Market Quality

      FVG supports medical device and complex electronics OEMs across the full product lifecycle, from design for manufacturability review through production, field-return management and manufacturing transfer. Its Malaysia facility operates under ISO 13485 and IPC-A-610 Class 3 workmanship standards, with in-house injection moulding, SMT assembly and box build integration under one quality management system.

      For OEM teams managing regulated or high-reliability products, FVG's post-market support capability includes:

      • Complaint handling and investigation: Structured 8D and non-conformance processes aligned to ISO 13485 and 21 CFR Part 820 requirements

      • Field return analysis: Physical failure analysis, environmental stress testing and lot-traceable root cause investigation

      • CAPA development and validation: Documented corrective actions with effectiveness verification before production resumption

      • Manufacturing transfer risk controls: Validated transfer processes for products moving between manufacturing sites or EMS partners, with full traceability continuity

      If your team is evaluating EMS partners for a regulated or high-reliability product programme, or managing an existing field-return situation that requires documented investigation support, contact FVG to discuss your specific requirements.